Not much going on in these forums lately, figured it might be a good time for a new topic. Anyway, I have been taking a few photos of the construction of the Green lift at Magic ever since the new ownership announced that they would be completing the lift. I thought I would share them here. But first, here are some older photos of the green lift that were taken in February of 2014. These show how complete the lift was prior to the more recent work done starting in spring 2017. If anyone is interested there are older pics of the lift on chairlift.org's magic page: http://www.chairlift.org/magic.html

Attached File(s)

  • Attached File  mag10.jpg (134.22K)
    Number of downloads: 95
  • Attached File  mag11.jpg (122.8K)
    Number of downloads: 113
  • Attached File  mag12.jpg (171.82K)
    Number of downloads: 100
  • Attached File  mag13.jpg (154.11K)
    Number of downloads: 99
  • Attached File  mag14.jpg (129.04K)
    Number of downloads: 98
  • Attached File  mag15.jpg (164.79K)
    Number of downloads: 93
  • Attached File  mag16.jpg (91.03K)
    Number of downloads: 90
  • Attached File  mag17.jpg (83.5K)
    Number of downloads: 68

-Sage


If life gives you lemons, make lemonade. And then find someone whose life is giving them vodka and have a party.
-Ron White

#2 skiersage

    SAM student

  • Administrator I
  • 858 Posts:

Posted 13 October 2018 - 09:18 AM

These next pictures are from the spring of 2017. This was back when the next round of work on the green lift was beginning.
Attached File  magic1.jpg (84.39K)
Number of downloads: 71
The above photo was from the folks at Magic when it was announced that the green lift would be completed. The green paint on the terminal was just for marketing as it was eventually painted over.
Attached File  mag1.jpg (106.14K)
Number of downloads: 90
Attached File  mag2.jpg (106.53K)
Number of downloads: 82
Attached File  mag4.jpg (143.61K)
Number of downloads: 83
The three above pictures were taken around may 1 2017. They show tower 1 with the un rebuilt sheaves assemblies still attached. In the latter pictures the sheaves on tower 1 are removed. The rest of the pictures were taken toward the end of may.

Attached File(s)

  • Attached File  mag3.jpg (98.54K)
    Number of downloads: 85
  • Attached File  mag5.jpg (137.98K)
    Number of downloads: 80
  • Attached File  mag6.jpg (127.6K)
    Number of downloads: 72
  • Attached File  mag7.jpg (144.95K)
    Number of downloads: 71
  • Attached File  mag8.jpg (200.49K)
    Number of downloads: 69
  • Attached File  mag9.jpg (160.88K)
    Number of downloads: 50

-Sage


If life gives you lemons, make lemonade. And then find someone whose life is giving them vodka and have a party.
-Ron White

#3 skiersage

    SAM student

  • Administrator I
  • 858 Posts:

Posted 13 October 2018 - 09:38 AM

These are the rest of the pictures I took during the summer of 2017. Most of the work done during this time was that both top and bottom terminals were disassembled so the components could be refurbished. The structural portions of the terminals were painted. the carriers were also refurbished during this time. Magic at the time was planning on opening this lift for the 2017-2018 ski season but weren't able to finish due to their contractor falling ill.

Attached File(s)


-Sage


If life gives you lemons, make lemonade. And then find someone whose life is giving them vodka and have a party.
-Ron White

#4 RibStaThiok

    Established User

  • Member
  • 1,057 Posts:

Posted 13 October 2018 - 09:17 PM

A lot of us can't wait for it to be finished and put into service. How long has it been since it was removed from Stratton?
Ryan

#5 skiersage

    SAM student

  • Administrator I
  • 858 Posts:

Posted 14 October 2018 - 06:07 AM

View PostRibStaThiok, on 13 October 2018 - 09:17 PM, said:

A lot of us can't wait for it to be finished and put into service. How long has it been since it was removed from Stratton?


The old betwixt lift was removed from Stratton in 1995. so that would mean t has been sitting idle for 23 years. Quite a while to say the least.

Here are my pics of from this summer 2018:
Attached File  mag20.jpg (92.93K)
Number of downloads: 74
Rebuilt sheaves hung on tower 1.
Attached File  mag21.jpg (132.99K)
Number of downloads: 91
tower 2 getting ready for sheaves.
Attached File  mag22.jpg (123.53K)
Number of downloads: 87
sheaves hung on tower 2.
Attached File  mag23.jpg (220.3K)
Number of downloads: 86
8 wheel rocker ready for installation. pretty sure this is the portal assembly for the light side.
Attached File  mag24.jpg (225.98K)
Number of downloads: 86
Return bullwheel getting ready for installation.
Attached File  mag25.jpg (153.07K)
Number of downloads: 88
bottom terminal with haul rope hung.
Attached File  mag26.jpg (151.08K)
Number of downloads: 89
haul rope now up.
Attached File  mag27.jpg (120.51K)
Number of downloads: 94
Portal assemblies.
Attached File  mag28.jpg (118.51K)
Number of downloads: 109
looking up the line with haul rope.
Attached File  mag29.jpg (145.73K)
Number of downloads: 94
This is the most recent photo I have taken (oct 9). It shows the motor room has been put up although missing some windows yet. The idler terminal sheaves were also installed since my last visit.