New Lift Construction Photos 2008
lastchair_44
14 Jul 2008
Rob, do you guys have to take that seat off the grip before entering the stations? How heavy is it?
Aussierob
14 Jul 2008
I haven't seen it in person, but I'm told it is reasonably easy to take on and off and does need to be removed before it comes into the station.
lastchair_44
14 Jul 2008
Yeah, thought you would have to take it off...it just looks like it would be kind of awkward. You'll have to post some photos when you get out there and have it in use!
Aussierob
15 Jul 2008
I'm hoping for a nice sunrise shot one day.
Couple of odd photos. This one is a cable spool at Fitzsimmons corner on the mountain road.
The convoy spun out here and they had to add the skidder to get it around the corner. You can't see it but there is another rock truck behind the red flat deck pushing.
DSC00110.JPG (2.12MB)
Number of downloads: 80
This winch is at the top of Whistler now to pull the haul ropes up once they're in the valley.
Winches__1_.JPG (442.74K)
Number of downloads: 65
I was going to put up a couple more but ran out of space. D'oh
This post has been edited by Aussierob: 15 July 2008 - 04:26 AM
Couple of odd photos. This one is a cable spool at Fitzsimmons corner on the mountain road.
The convoy spun out here and they had to add the skidder to get it around the corner. You can't see it but there is another rock truck behind the red flat deck pushing.
DSC00110.JPG (2.12MB)
Number of downloads: 80
This winch is at the top of Whistler now to pull the haul ropes up once they're in the valley.
Winches__1_.JPG (442.74K)
Number of downloads: 65
I was going to put up a couple more but ran out of space. D'oh
This post has been edited by Aussierob: 15 July 2008 - 04:26 AM
skier2
15 Jul 2008
When were those pictures taken? Those have to have been from a while ago, right, because otherwise the amount of snow remaining on the lower portion of Whistler is insane.
skisox34
16 Jul 2008
If you have a job opening for the line checker on the 3s, I volunteer!!!!
Andoman
16 Jul 2008
Well maybe not as interesting as the p2p or any larger projects, our lovely michigan resort, Nub's Nob has a picture of them setting the base area terminal supports for the new used superior tramway triple chair. Picture from nubsnob.com
Attached File(s)
-
nubsnobinstall.jpg (38.69K)
Number of downloads: 58
skier2
16 Jul 2008
So I guess this doesn't run exactly parallel to the current Pintail Peak chair, then, but close? Is this correct?
Andoman
16 Jul 2008
skier691
16 Jul 2008
Callao
17 Jul 2008
PCMR is making progress cutting the line for the new Crescent HSQ. This is a pic I took from the Marriott roof a couple days ago. They are digging out tower footings.
IMG_7023.jpg (268.62K)
Number of downloads: 103
IMG_7023.jpg (268.62K)
Number of downloads: 103
floridaskier
18 Jul 2008
Are they not planning to remove the old Ski Team lift this summer? It looks like they won't have to take it out to make room for the new lift
Peter
18 Jul 2008
Lots of pictures of Chair 1 at Mt. Baker: http://www.mtbaker.us/gallery/main.php
SuperRat
20 Jul 2008
There are a few photos of Killington's new Skye Peak Express: http://www.killingto...ountain/gallery
Callao
20 Jul 2008
floridaskier, on Jul 18 2008, 11:37 AM, said:
Are they not planning to remove the old Ski Team lift this summer? It looks like they won't have to take it out to make room for the new lift
I'm not sure about Ski Team. But it looks like Crescent will go nearly right over Ski Team's bottom terminal. As far as I understand, Crescent's bottom terminal will be just down-run of that mountain coaster bridge.
floridaskier
20 Jul 2008
It looks like the bottom is going right next to the end of the Ziprider, parallel with the bottom of Payday. The website says the new lift replaces Ski Team, but they haven't touched it yet so who knows.
Snoqualmie guy
21 Jul 2008
The Silver Fir Pictures are up on the Snoqalmie Summit site.
This post has been edited by Snoqualmie guy: 21 July 2008 - 06:50 AM
This post has been edited by Snoqualmie guy: 21 July 2008 - 06:50 AM
SuperRat
21 Jul 2008
floridaskier, on Jul 21 2008, 03:09 AM, said:
It looks like the bottom is going right next to the end of the Ziprider, parallel with the bottom of Payday. The website says the new lift replaces Ski Team, but they haven't touched it yet so who knows.
Is this Ski Team listed on Mad River Lifts: Yan for Sale
Peter
21 Jul 2008
Yes. There are a lot of lifts on there that are still standing/operating and for sale. A bunch of Squaw Valley backup lifts are for sale with removal to be done by the buyer.