Sure, they could splice ... but I guess it comes down to a question of cost ... plus insurance may want a new rope just because ...

(no way to tell how long it ran w/the rope passing through flames, either ... might make the insurer nervous)

This doesn't happen often in the lift-world, so I'd bet there is a lot of learning going on "in the biz" from this event.
Reply

_litz's Photo _litz 10 Dec 2016

Couple of pictures from this news report:

http://www.wbir.com/...amage/367420882

Posted Image

Posted Image

That looks a lot more like soot damage to me, then actual heat "burned the paint off" damage ...

Either way, that's one incredibly durable, tough piece of Riblet engineering.
Reply

_litz's Photo _litz 06 Feb 2017

Peter has news ...

https://liftblog.com...-in-gatlinburg/

Have to wonder how much "new" can be done in two months ...

here's an Instagram picture from last December showing the top terminal damage

https://www.instagra.../p/BN4Nr4DDikB/
This post has been edited by _litz: 06 February 2017 - 03:46 PM
Reply

Keymech's Photo Keymech 07 Feb 2017

Correct me if I am wrong, but the lift in the pictures ( Riblet ) has nothing to do with the article that was posted by litz.
Reply

_litz's Photo _litz 07 Feb 2017

Actually it is ... the 'original' Gatlinburg Sky Lift (it's actually the 2nd lift on that site) was a yellow/orange Riblet double chair.

The top terminal was completely crisped by the fire; only the fact that they had left the lift running when they evacuated likely kept the haul rope from parting from the heat.

Note sure if their plans are a whole new lift from scratch, or a repair/rebuild of the existing one (plenty of riblet parts out on the market, for sure), but they have plans to replace/fix both the lift, and build a much larger attraction around it.

Their whole top-of-lift property was incinerated, so they have a clean slate to build whatever they want.
Reply

RibStaThiok's Photo RibStaThiok 07 Feb 2017

It will be a new Doppie triple according to Peter's site.
Reply

_litz's Photo _litz 07 Feb 2017

Cool ... now we have to wait and see if it has orange towers and yellow chairs like the Riblet did ...
Reply

_litz's Photo _litz 15 Feb 2017

Looks like rebuilding is getting underway in Gatlinburg ... several projects up before their planning board including Boyne's project for the Skylift :

http://gatlinburgtn..../view,download/
Reply

_litz's Photo _litz 08 Mar 2017

Update from Peter's weekly news briefs ...

http://www.wbir.com/...-lift/420216214

Work is underway, plan is to open mid April. Orange towers and yellow chairs.
Reply

_litz's Photo _litz 22 Mar 2017

More news (courtesy LiftBlog) ... no question about that orange!

http://wate.com/2017...-lift-in-april/