Local article on the Snowbird Tram cable replacement this spring


  • You cannot reply to this topic
31 replies to this topic

#1 RibStaThiok

    Established User

  • Member
  • 1,057 Posts:

Posted 31 March 2016 - 01:38 AM

http://www.ksl.com/?...-tramcar-cables
Ryan

#2 Vincen

    Established User

  • Member
  • 34 Posts:
  • Interests:ski lifts and resorts

Posted 31 March 2016 - 02:07 AM

Nice update of the tram ;)

#3 SkiDaBird

    Established User

  • Member
  • 509 Posts:
  • Interests:Skiing

Posted 31 March 2016 - 03:20 PM

Nice find.

#4 JSteigs

    Established User

  • Industry II
  • 115 Posts:

Posted 01 April 2016 - 07:32 AM

I am guessing that they are replacing the track ropes since they mention they are replacing four ropes. They also say that the tram will pull the new ropes. I am curious as to how they would do that. Has anyone here been apart of track rope replacement like this? I have been apart of new haul rope installation, and haul rope replacements but never work with track ropes.

#5 _litz

    Established User

  • Member
  • 154 Posts:

Posted 01 April 2016 - 02:07 PM

They do talk about closing the area underneath the tram ... maybe they're going to pull the new cable up the mountain, then after it's pulled, lift it up onto the towers?

(since it's stationary, there's no real easy way to haul it across the towers, like you would with a haul rope)

#6 SkiDaBird

    Established User

  • Member
  • 509 Posts:
  • Interests:Skiing

Posted 01 April 2016 - 02:43 PM

http://www.snowbird.com/tramcables/
Not a lot of details here, but a few things not mentioned in the KSL article.

#7 liftmech

    lift mechanic

  • Administrator II
  • 5,918 Posts:
  • Interests:Many.

Posted 01 April 2016 - 05:45 PM

I'm guessing the cables will be pulled, one at a time, by the cabins. There will be many additional items to take care of, such as slack carriers and obviously placing the track ropes on the towers. Looks like a fun project!
Member, Department of Ancient Technology, Colorado chapter.

#8 monkey

    Established User

  • Industry II
  • 56 Posts:
  • Interests:little cottonwood deep powder skiing

Posted 02 April 2016 - 07:15 PM

I think K.O. Was misquoted in regards to using the cars to pull the new ropes. Our plan is to socket the new rope to the old rope. Lift the haul rope off the sheaves, and pull it to the side on all towers. Then move the old rope off the saddle and down on to the sheaves, so in a sense use the tower sheave much as you would for a haul rope replacement. Then we will pull the old and new ropes to the Peak. Put the new rope on the saddles and repeat. Sounds pretty simple huh!

#9 _litz

    Established User

  • Member
  • 154 Posts:

Posted 03 April 2016 - 06:32 PM

Wow, what a neat and simple idea!

#10 JSteigs

    Established User

  • Industry II
  • 115 Posts:

Posted 04 April 2016 - 04:49 AM

View Postmonkey, on 02 April 2016 - 07:15 PM, said:

I think K.O. Was misquoted in regards to using the cars to pull the new ropes. Our plan is to socket the new rope to the old rope. Lift the haul rope off the sheaves, and pull it to the side on all towers. Then move the old rope off the saddle and down on to the sheaves, so in a sense use the tower sheave much as you would for a haul rope replacement. Then we will pull the old and new ropes to the Peak. Put the new rope on the saddles and repeat. Sounds pretty simple huh!



Thanks for the info. That is the idea that makes the most sense. Do you expect the socket to pass over the sheaves easily, from what I remember they are pretty large.

#11 monkey

    Established User

  • Industry II
  • 56 Posts:
  • Interests:little cottonwood deep powder skiing

Posted 04 April 2016 - 05:59 PM

So the existing sockets will be removed after the counterweights are lifted and the track rope we are pulling is rigged and detensioned in the station. We then pour new sockets on both the new and old ropes and use a special connection intended for the job, to attach the two. The new ropes will be staged to the north of the bottom station, then fed through the station and up the hill. Meanwhile at the Peak the winch, horizontal spooler,etc will be below the top station and above tower 4. The plan is to deflect off the top saddle and pull the ropes back downhill, when we get what we need then up and over and around the ballards.
I know I am breezing over a lot the smaller details like all slack carriers on the ground or the fact we still have 100"+ base, but I just want to give the basic ideas involved. We jokingly call this type of a job as "camping", and we expect Mother Nature to have her say and give us another 100" of snow during this job. There will be plenty of photos taken and I will post some.

#12 JSteigs

    Established User

  • Industry II
  • 115 Posts:

Posted 05 April 2016 - 06:02 AM

View Postmonkey, on 04 April 2016 - 05:59 PM, said:

So the existing sockets will be removed after the counterweights are lifted and the track rope we are pulling is rigged and detensioned in the station. We then pour new sockets on both the new and old ropes and use a special connection intended for the job, to attach the two. The new ropes will be staged to the north of the bottom station, then fed through the station and up the hill. Meanwhile at the Peak the winch, horizontal spooler,etc will be below the top station and above tower 4. The plan is to deflect off the top saddle and pull the ropes back downhill, when we get what we need then up and over and around the ballards.
I know I am breezing over a lot the smaller details like all slack carriers on the ground or the fact we still have 100"+ base, but I just want to give the basic ideas involved. We jokingly call this type of a job as "camping", and we expect Mother Nature to have her say and give us another 100" of snow during this job. There will be plenty of photos taken and I will post some.


I look forward to the pics.

#13 liftmech

    lift mechanic

  • Administrator II
  • 5,918 Posts:
  • Interests:Many.

Posted 09 April 2016 - 05:27 PM

Definitely. Paid for a tour with a 30-rack a few years back, was impressed by the size of your marquee lift. Makes the size of the project that much bigger.
Member, Department of Ancient Technology, Colorado chapter.

#14 monkey

    Established User

  • Industry II
  • 56 Posts:
  • Interests:little cottonwood deep powder skiing

Posted 10 April 2016 - 05:11 AM

Always happy to give a tour!

#15 monkey

    Established User

  • Industry II
  • 56 Posts:
  • Interests:little cottonwood deep powder skiing

Posted 01 May 2016 - 06:51 PM

A few pictures of week 1, which was spent getting everything staged. Overtime is in abundance.

Attached File(s)



#16 RibStaThiok

    Established User

  • Member
  • 1,057 Posts:

Posted 02 May 2016 - 09:16 AM

Got a Bell Jet Ranger III doing the work, eh?
Ryan

#17 Lift Dinosaur

    Established User

  • Industry II
  • 2,076 Posts:

Posted 02 May 2016 - 01:46 PM

View PostRibStaThiok, on 02 May 2016 - 09:16 AM, said:


Got a Bell Jet Ranger III doing the work, eh?

Looks like an A-Star to me....
Dino
"Things turn out best for the people that make the best of the way things turn out." A.L.

#18 RibStaThiok

    Established User

  • Member
  • 1,057 Posts:

Posted 03 May 2016 - 07:10 PM

yup your right. I should have looked closer at the main rotor head.
Ryan

#19 monkey

    Established User

  • Industry II
  • 56 Posts:
  • Interests:little cottonwood deep powder skiing

Posted 06 May 2016 - 06:37 PM

The rigging of tower 2. Pulling a 14 mm rope spliced to a 22 mm rope for the reave, that when done is then pulled 50 meters uphill to detension track rope #1. A view from the ride to torque the plate clamps. I have many more photos and much more progress has been made but I don't have to much spare time right now to post them all.

Attached File(s)



#20 monkey

    Established User

  • Industry II
  • 56 Posts:
  • Interests:little cottonwood deep powder skiing

Posted 08 May 2016 - 06:59 AM

Last night we landed the new rope on bollard 1. The weather has been mostly rain, lightning, snow, wind, lightning, wet slides the an hour or two of sun followed by more snow. We hope for better weather to come. In the first picture you can see the socket making its way over the first set of rollers on tower 1 notice the nice weather, so you can get all sweaty climbing towers. Then the socket making its way through the trees in Mid-Cirque between towers 3 & 4. Crossing tower 4. Then resetting the milking machine (A brillant piece of equipment that I will explain later) to clear the socket, notice more snow. One last one of Peter aka the Amazing Spider-Man!

Attached File(s)